Step 1: Verify Your Delivery Against the Packing Slip (Before You Unwrap Anything)
-
Step 2: Confirm the Contents Against the Installation Manual
-
Step 3: Check On-Site Conditions Against the Unit Requirements
-
Step 4: Do a "Dry Run" of the Software Integration
-
Step 5: Identify Responsibility Boundaries Before the Installation
-
Final Notes: Two Things to Watch Out For
If you're reading this, you've probably just signed off on a new Planmeca unit—maybe a dental chair, maybe a ProX imaging system. Congratulations. It's good equipment. But I'm writing this because, in my experience, the real cost of dental equipment isn't the price tag. It's what happens between delivery and the moment your first patient sits down.
I'm a procurement manager for a mid-sized dental services group. I've managed our equipment budget for over 6 years and tracked roughly $180,000 in cumulative spending across dozens of installations, from Planmeca chairs to CBCT units. And I've made expensive mistakes. This checklist is the result of those mistakes.
Here's the thing: most issues are preventable. But you have to check the right things before you sign off. This guide covers 5 steps you should follow—starting from the moment the crates arrive.
Step 1: Verify Your Delivery Against the Packing Slip (Before You Unwrap Anything)
When the delivery truck shows up, it's tempting to have the crew start unwrapping immediately. Don't. I've done this. First mistake I learned the hard way involved a Planmeca ProX unit where the main gantry was damaged. Because we'd already accepted the shipment and started unboxing, proving it wasn't our fault became a three-week fight with the freight company. That delay cost us an estimated $2,400 in lost chair time.
Instead, follow this process:
- Pull up the packing slip. Check the model numbers match your order. Check the serial numbers too—I've seen a hospital receive the wrong configuration because the packing slip matched but the serial didn't.
- Inspect the external crates for any signs of damage: dents, punctures, water stains. Take photos of every side of every crate before opening.
- If there's noticeable damage, don't refuse the shipment outright. Note it on the delivery receipt. Get the driver's signature. Then proceed with unboxing and detailed inspection.
This is a classic 5-minute check that can save you weeks of headache. I should add: if you ever need to file a claim, having photos dated before unboxing is your golden ticket.
Step 2: Confirm the Contents Against the Installation Manual
Once the crates are opened, don't just look for the obvious big pieces. You need to cross-check every component against the Planmeca ProX installation manual or the Planmeca dental chair manual that came with your unit.
What most people don't realize is that these manuals include a detailed parts checklist at the beginning. It lists every cable, bracket, screw, and mounting rail. I've found missing items twice:
- Once, a specific bracket for the monitor arm was missing. It took 10 days for the replacement to arrive. Because we didn't catch it until the installation tech showed up, we had to reschedule the install.
- Another time, a critical cable for the EMS (electrical medical system) interface was included but the wrong revision. It fit, but it wasn't the correct spec for our network.
The process:
- Open the manual to the parts list page.
- Check off each item as you locate it in the packaging. Don't rush this.
- If something is missing or unclear, don't assume it's okay. Call your vendor or Planmeca support immediately. Better to catch it before the installer arrives than to pay for a second service call.
Step 3: Check On-Site Conditions Against the Unit Requirements
This is the step where most of the hidden costs live. Every Planmeca unit has specific requirements for power, water, compressed air, and network connectivity. If your site doesn't meet them, you'll face costly delays and emergency contractor fees.
Let me give you a real example from our clinic in 2023. We installed a Planmeca ProMax 3D unit. The manual specified a dedicated 20-amp circuit. Our site had a shared 15-amp circuit. The electrical contractor quoted us $1,200 to run a new line. That was our fault—we should have checked the specs before the room was ready.
Here's a quick checklist for your site walkthrough:
- Power: Confirm voltage and amperage requirements. Check the manual for dedicated circuit requirements. If you're not sure, an electrician is cheaper than a delayed install.
- Compressed air: Dental chairs need dry, oil-free air at a specific pressure range. Does your existing compressor meet that? If not, you might need a dedicated line or a booster.
- Water supply and drainage: Check the connection sizes and flow requirements. A standard dental chair is usually fine, but some units require a higher flow rate for the intraoral scanner cooling system.
- Network: For Planmeca imaging systems, network consistency matters. A flaky Wi-Fi connection will cost you more than running a CAT6 cable.
Put another way: if you're dealing with a space that was built within the last 10 years, you're probably fine. If it's a retrofit in an older building, expect surprises.
Step 4: Do a "Dry Run" of the Software Integration
This one is a bit different. By now, you might be thinking, "We've checked the physical items, we're good." But I've learned that software integration is where the serious hidden costs live.
When I audited our 2023 spending, I found that 34% of our installation budget overruns came from software integration issues. Not hardware problems. Not missing parts. Software.
Here's what I recommend:
- Before the installation tech arrives, have your IT person or software lead read through the software setup section of the manual. Identify any prerequisites: operating system versions, database requirements, specific DICOM or HL7 settings.
- Set up a test terminal (or configure the designated workstation) with the required specs before the installation day. This includes installing any needed middleware or drivers.
- If you're integrating with an existing practice management software (like Dentrix or Eaglesoft), confirm that the version you're using is supported. One clinic I know tried to integrate a new Planmeca CBCT with an older, unsupported version of their PMS. They had to pay a third-party consultant $3,500 to write a custom bridge. (Should mention: they had the PMS vendor's documentation all along; they just hadn't checked it.)
The key here is that once the imaging unit is physically installed, you're paying the technician by the hour. Having software issues during that time is the most expensive way to discover you didn't prepare.
Step 5: Identify Responsibility Boundaries Before the Installation
Here's something vendors won't tell you: the installation contract usually covers only the direct assembly and connection of the unit. Anything beyond that—running new wiring, upgrading your network switch, repairing a water line—is going to cost you extra, and it may require a separate contractor.
I recommend asking your vendor or Planmeca representative for a clear responsibility matrix before anyone shows up. Questions to ask:
- Who is responsible for providing the electrical drop to the unit?
- Who runs the network cable from the unit to your server room or switch?
- Who handles the initial calibration? Is that included in the install price?
- What about training for the software? Is it included, and how long does it last?
The cheapest way to handle this is to get all of these questions answered in writing. If the answer is "your contractor," that's fine. But you want to know that before the install, not during.
Final Notes: Two Things to Watch Out For
1. Don't trust the "guaranteed" installation timeline. The timeline your vendor quotes is often based on ideal conditions. Plan for the install to take 1.5x the quoted time. If it finishes early, you've gained a bonus. If it doesn't, you won't be scrambling to reschedule patients.
2. Keep the original packaging until the installation is signed off. I've had two instances where we needed to return a component due to a defect. Having the original box and foam inserts made the RMA process much smoother.
This approach worked for us, but our situation is a mid-size group with predictable ordering patterns and a dedicated IT person. If you're a solo practice doing your first install, the calculus might be different—you might need to be more hands-on with each step. The core principle stays the same: spend 30 minutes checking before the install, and you'll save days and thousands of dollars.